#41 – 9/20/2023 Septic Continued…
Hey all! I did make it to the land the last two Saturdays and made some progress on the septic system (work kicked in OT so my play time is a pretty limited). Here are some pictures and a couple of… Continue reading
-
#40 – 9/3/2023 – Oh Crap!
This week I am determined to be brief! And don’t worry about the newsletter title. I couldn’t come up with anything witty, and since I have been working on my septic, that is what came to mind. And that’s it… Continue reading
-
#34 – 10/29/2022 – Leach Field Done… Mostly.
Another week! Man they are coming and going so fast. I feel like I’m running out of time to get things ready for the spring! I was able to get a decent amount done this weekend! I was a little… Continue reading
-
#33 – 10/23/2022 – A Change in Seasons
Utah weather ceases to amaze me! For those not local to Utah in the space of 48 hours we went from a high of 75 degrees to a high of 39 (in Huntsville) with snow flurries! Up to this point,… Continue reading
-
#32 – 10/16/2022 – Rock On!
I haven’t had a ton of time out at the land lately, but I did get out there on Tuesday this last week for our gravel delivery for the septic leach field. And we had quite a bit of gravel… Continue reading
-
#31 – 10/02/2023 – Back on Track
Hi all! Good news! The excavator chain installation was completed late Thursday night! I got chased around a little bit by some rain which made the final 16 trackpad installation a bit muddy and annoying. However, I got it done and… Continue reading